TABLE 1.2. Task schedule from a project that switches from face-to-face to layered collaboration

Deadline Who Task
3/02 Everyone Initial group meeting
3/04 Everyone Group meeting
3/04 Stephen E-mail schedule and notes from group meeting
3/13 Tim Complete client interviews; e-mail interview notes to the group
3/14 Everyone Group meeting at 3:00 p.m. to discuss interviews
3/14 Stephen E-mail notes from group meeting
3/21 Charlotte E-mail rough draft of requirements document minus introduction and conclusion
3/23 Tim E-mail comments on requirements document
3/29 Stephen E-mail revised draft of requirements with introduction and conclusion added
3/31 Tim E-mail draft of cover letter addressed to client
4/03 Charlotte E-mail revised and polished draft of all materials to group for last-minute comments
4/04 a.m. Stephen E-mail editing suggestions to Charlotte
4/04 p.m. Charlotte Turn in final draft to professor by 3:00 p.m.