Question 3.5

5. Given the accompanying order-requirement digraph (time in minutes) and the priority list T6, T5, T4, T3, T2, T1, apply the list-processing algorithm to construct a schedule using two processors. The completion time of the resulting schedule is __________________________.

image

5.

14 min