Question 3.7

7. Suppose that a crew can complete in a minimum amount of time the job whose order-requirement digraph is shown below. If task T2 is shortened from 5 minutes to 1 minute, then the maximum amount by which the completion time for the entire job can be shortened is _________________________.

image

7.

2 min