Question 4.115

4.115 Managing new-product development process.

Exercise 4.113 (page 228) gives the distribution of time to complete two steps in the new-product development process.

  1. Calculate the variance and the standard deviation of the number of weeks to complete the development of product specifications.
  2. Calculate and for the design of the manufacturing-process step.